Deeper Understanding

Host System Parameters for each host system

Modified on Thu, 12 Nov at 10:26 AM

TABLE OF CONTENTS

  1. Introduction
  2. Safran sending
  3. Safran receiving
  4. P6 sending
  5. P6 receiving
  6. Microsoft Project sending
  7. SAP sending
  8. SAP receiving
  9. ILAP Analytics sending
  10. ILAP Analytics receiving
  11. Generic REST API sending
  12. Generic REST API receiving
  13. File Storage sending
  14. Settings that several host systems share

Introduction

Host System Parameters (HSPs) control how SchedEx reads a schedule from your host system (sending) and how it writes a schedule into it (receiving). Each Config has its own parameters, on the Host System Parameters tab. Sending and receiving Configs have different parameters.

When you create an Exchange Agreement (EA), the Config's parameters are copied into the EA as its starting values. You can then change them on the EA for that agreement only. Because of this, a later change to the parameters in the Config is not passed on to existing EAs, and no update indicator is shown on the EA.

Each section below shows a screenshot with red numbers, followed by a table that explains each numbered setting. Use the table of contents to jump to your host system and direction.

Which host systems have parameters:

  • Safran, Primavera P6, ILAP Analytics and Generic REST API have parameters in both directions.
  • SAP has parameters in both directions. On the sending side they are only the two analysis switches.
  • Microsoft Project has parameters for sending only. Receiving into Microsoft Project is not supported.
  • File Storage has parameters for sending only.
  • Microsoft Excel has no Host System Parameters.

Safran sending

The Host System Parameters of a Safran sending Config, in edit mode.

#SettingWhat it does
1Export ScopeWhich set of Safran fields is used to fill these SchedEx core fields on upload: Early Start/Finish, Late Start/Finish, Actual Start/Finish, Planned Work Hours and Planned Progress. Choices: Total, Baseline, Current and Revised. The details are in What data does Safran upload based on Scope parameter?.
2Resource Assignment Export OptionAll: every resource assignment is uploaded, whatever the scope flags. Scope Dependent: only the resource assignments that match the sending schedule's Project Properties scope are uploaded (after a Status Update has been run in Safran).
3R Fields Export OptionWhich R-field values are included in the upload. Export only values used (default): only the values that uploaded activities refer to. Export all values in referenced RField: every value of each R-field that an uploaded activity uses. The extra values can be appended to another Safran schedule's R-fields or a P6 schedule's activity codes.
4WBS StructureThe R-field or Outline Code to use as the Work Breakdown Structure (WBS). Useful when P6 receives the schedule.
5Other StructuresOther R-fields or Outline Codes to upload as structures, even when no activity uses them. The receiving side can use them to append values to its own structures (R-fields in Safran, activity codes in P6).
6Set 'Start No Earlier Than' (SNET)When to add a Start No Earlier Than constraint to activities that arrive without predecessors. See More info on: Set 'Start No Earlier Than' (SNET) below.
7Get activities in batchRead activities from Safran in batches. The batch size is set on the connector and is 10,000 by default.
8Enable non-ascii character analysisSee Settings that several host systems share.
9Enable conflict analysisSee Settings that several host systems share.

More info on: Set 'Start No Earlier Than' (SNET)

The earlier Safran sending checkbox Use SNET When No Predecessors is now a dropdown named Set 'Start No Earlier Than' (SNET). When a transfer sends a schedule out of Safran, an activity that arrives without predecessors has nothing holding its start date, so the receiving system can move it earlier. This setting adds a Start No Earlier Than constraint to prevent that. The constraint uses the activity's Early Start date in Safran. An activity with an empty Early Start is never constrained.

The dropdown has three options:

  • Never (default): no SNET constraint is added. This matches the old checkbox turned off.
  • When an activity has no predecessors: constrains every transferred activity that has no predecessors among the transferred activities. This matches the old checkbox turned on.
  • When predecessors are missing or removed by the filter: does the above, and also constrains an activity that lost at least one predecessor because the activity filter excluded it.

The transfer log reports which option was used and which activities were constrained or skipped. Existing Configs were converted automatically: a checked box became When an activity has no predecessors, and an unchecked box became Never. The third option needs an up-to-date Desktop Client or Autonomous Component, and the receiving Config must map the Start No Earlier Than field for the constraint to be written.


Safran receiving

The Host System Parameters of a Safran receiving Config, in edit mode.

#SettingWhat it does
1Allow Append CalendarsAllow new calendars from the sender to be added to the receiving schedule. Turn it off if you map calendars to calendars that already exist in your schedule.
2Allow Appending Duplicate CalendarsAllow an incoming calendar to be added even when a calendar with the same name already exists. The new calendar gets a numbered suffix: "_1", then "_2", and so on. If an identical calendar already exists, no new calendar is added. When this is off, the calendar isn't added and the default calendar (the first calendar in the receiving schedule) is used instead.
3Allow Appending TasksAllow new activities to be added. When this is off, only existing activities are updated.
4Allow Append ResourceAllow new resources to be added. Turn it off if you map or hard-code each resource assignment's resource to a resource that already exists in your schedule.
5Allow Append StructuresAllow missing R-field values from the sender to be appended to existing R-fields. Existing values are not changed.
6Allow Update Of Structure DescriptionAllow incoming data to change the descriptions of structure values that already exist.
7Allow Updating Existing ProfilesAllow profile data to be added or updated in the receiving schedule.
8Only Include Specified MappingsSee Settings that several host systems share.
9Set Activity Duration Fit to FalseTurn off Safran's Duration Fit on imported activities. Duration Fit stretches an activity to fill the time between its predecessors and successors, which can change imported dates and Planned Work Hours.
10Activity Link Rebuild OptionSee Settings that several host systems share.
11Resource Assignment Rebuild OptionSee Settings that several host systems share.
12Duplicate Resource Assignment OptionWhat happens when an incoming resource assignment uses a resource that is already assigned to the activity. Update existing with incoming (default): the existing assignment is updated. Add incoming as new: a second assignment is added. Do not add incoming: the incoming assignment is skipped, and the transfer log says so. If a rebuild option is set (11), the rebuild runs first, and assignments it deleted don't count as duplicates.
13Calendar PrefixText added in front of the names of incoming calendars, for example "XXX_", so they are easy to recognize and don't overwrite your own. This only takes effect if it is set before the first transfer. Changing it later has no effect.
14Enable conflict analysisSee Settings that several host systems share.
15Use synthetic resource in absence of resource assignmentUse this when the sending schedule has planned hours on activities but no resource assignments. A resource is then added, with one resource assignment per activity, so the hours reach Safran.
16Structure / R-Field (structure mappings)Which incoming structure appends its missing values to which Safran R-field. When you edit the Config, select + Add new above the grid to add a mapping row. You can add as many mappings as you need.

P6 sending

The Host System Parameters of a P6 sending Config, in edit mode.

#SettingWhat it does
1WBS StructureThe P6 global activity code to upload as the WBS. Even if you leave this empty, the schedule's existing WBS is uploaded. Only use it to replace the existing WBS with an activity code.
2Other StructuresOther P6 activity codes, global or project, to upload. The receiving side can use them to append values to R-fields in Safran or to activity codes in another P6 project.
3Get activities in batchRead activities from P6 in batches. The batch size is set on the connector. Not shown for P6 XER File connectors.
4Enable non-ascii character analysisSee Settings that several host systems share.
5Enable conflict analysisSee Settings that several host systems share. Not shown for P6 XER File connectors.

P6 receiving

The Host System Parameters of a P6 receiving Config, in edit mode.

#SettingWhat it does
1Allow appending tasksAllow new activities to be added. Default on.
2Allow append resourceAllow new resources to be added. Turn it off if you map or hard-code each resource assignment's resource to a resource that already exists in your schedule. Default on.
3Allow appending calendarsAllow new calendars to be added. Turn it off if you map calendars to calendars that already exist in your schedule. Default on.
4Allow appending structuresAllow missing activity code values from the sender to be appended to existing activity codes. Default on.
5Do not import WBSKeep your project's existing WBS instead of importing the sender's. Default off.
6Only Include Specified MappingsSee Settings that several host systems share. Default off.
7Link OptionsHow activity links are recreated. See Activity Link Rebuild Option in Settings that several host systems share.
8Resource Assignment Rebuild OptionsSee Settings that several host systems share.
9Adjust LagsDefault off. In P6 you can't choose which calendar a link uses. P6 uses the successor's or the predecessor's calendar, or a 24-hour calendar, according to its "Calendar for scheduling Relationship Lag" setting. When this is on, SchedEx reads that setting and adjusts each lag, so the dates stay as close as possible to the sending schedule after you reschedule (F9).
10Enable conflict analysisSee Settings that several host systems share. Default on.

The P6 scheduling setting that Adjust Lags reads.

More about this in How lags may be auto-adjusted in P6 to give same result as Safran.

P6 XER File connectors only show Do not import WBS, Only Include Specified Mappings, Link Options and Adjust Lags on the receiving side.


Microsoft Project sending

The Host System Parameters of a Microsoft Project sending Config, in edit mode.

#SettingWhat it does
1Include summary task(s)Also upload summary tasks (the rolled-up parent rows), not just the detail activities.
2WBS StructureThe Outline Code or Text field to upload as the WBS. Useful when P6 receives the schedule.
3Other StructuresOther Outline Codes and Text fields to upload alongside the WBS.
4Enable non-ascii character analysisSee Settings that several host systems share.
5Enable conflict analysisSee Settings that several host systems share.

Receiving into Microsoft Project is not supported, so there are no receiving parameters.


SAP sending

An SAP sending Config has two parameters: Enable non-ascii character analysis and Enable conflict analysis. See Settings that several host systems share.


SAP receiving

The Host System Parameters of an SAP receiving Config, in edit mode, with the SAP Function Setup grid.

#SettingWhat it does
1Only Include Specified MappingsSee Settings that several host systems share.
2Stop on errorTurn this on to stop the transfer when SAP returns an error.
3SAP Function SetupRules that set statuses on SAP work orders and operations while data is written. Select + Add row to add a rule. See the columns below.

The SAP Function Setup grid has these columns:

ColumnWhat it means
IndexSorts the rules and decides the order they run in. System status rules run first, then user status rules.
Object TypeOrder or Operation: whether the status is set on the work order or on one of its operations.
Function TypeSystemStatus (SAP's built-in statuses) or UserStatus (statuses your company has set up in SAP).
ContextUpdate or Create: whether the rule runs when the item is updated or when it is created.
Sequence TypeWhen the rule runs: Before Confirmations, Before Update or After Confirmations.
Condition FormulaOptional. The rule only runs when the formula is true. Two extra variables are available: HasActuals (true when ActualWorkHours is more than 0) and OrderIsComplete (true when every operation has Progress 100%). Example: (OPR_ReadyForExecution == "x") && HasActuals
ParameterThe status to set, as plain text without quotes. The valid values depend on your SAP system; ask your SAP administrator.
Set inactiveFor user status rules only: when checked, the user status is reset (made inactive) in SAP instead of set. System status rules show "n/a".
ExcludedWhen checked, the whole row is ignored. This works the same as deleting the row. Excluded needs Desktop Client or Autonomous Component 2.17.0.0 or later. On an older client the row still runs and is still sent to SAP.

ILAP Analytics sending

The Host System Parameters of an ILAP Analytics sending Config, in edit mode.

#SettingWhat it does
1Revision TypeWhich revision type to upload: Live, Original Baseline, Baseline or Current/Revised. The most recently downloaded schedule of that revision type is uploaded.
2Enable non-ascii character analysisSee Settings that several host systems share.
3Enable conflict analysisSee Settings that several host systems share.

ILAP Analytics receiving

The Host System Parameters of an ILAP Analytics receiving Config, in edit mode.

#SettingWhat it does
1Revision TypeWhich revision type the downloaded schedule is stored as: Live, Original Baseline, Baseline or Current/Revised.
2Adjust CutoffWhen this is on, the cutoff date (the date progress is reported up to) in ILAP Analytics is set automatically, based on the Cutoff Adjustment Types setting (3).
3Cutoff Adjustment TypesScheduled Transfer Date (default): uses the EA's scheduled transfer date and finds the closest earlier cutoff in ILAP Analytics, according to the report schedule's "Points in time type". Host System Cutoff: uses the cutoff date of the sending host system (only Safran and Microsoft Project have one) and finds the nearest matching date in ILAP Analytics, forwards or backwards. For example, a cutoff on Sunday at 00:00 is moved to the following Monday at 00:00 to match the cutoff in ILAP Analytics.

The "Points in time type" of a report schedule in ILAP Analytics.


Generic REST API sending

The Host System Parameters of a Generic REST API sending Config, in edit mode.

#SettingWhat it does
1Revision TypeWhich revision type (version) of the schedule the transfer represents: Live, Original Baseline, Baseline or Current/Revised.
2Export All ResourceSend every resource defined in the schedule, also resources that no uploaded activity uses.
3Export All CalendarsSend every calendar defined in the schedule, also calendars that no uploaded activity uses.
4Get activities in batchRead activities from the API in batches. The batch size is set on the connector.
5Enable non-ascii character analysisSee Settings that several host systems share.
6Enable conflict analysisSee Settings that several host systems share.

Generic REST API receiving

The Host System Parameters of a Generic REST API receiving Config, in edit mode.

#SettingWhat it does
1Revision TypeWhich revision type (version) of the schedule the transfer represents: Live, Original Baseline, Baseline or Current/Revised.
2Allow Append CalendarsAllow new calendars from the sender to be added.
3Allow Appending TasksAllow new activities to be added. When this is off, only existing activities are updated.
4Allow Append ResourceAllow new resources to be added.
5Only Include Specified MappingsSee Settings that several host systems share.
6Calendar PrefixText added in front of the names of incoming calendars, so they are easy to recognize and don't overwrite your own.
7Enable conflict analysisSee Settings that several host systems share.

File Storage sending

A File Storage sending Config has two parameters: Enable non-ascii character analysis and Enable conflict analysis. See Settings that several host systems share.


Settings that several host systems share

SettingWhereWhat it does
Enable non-ascii character analysisSendingChecks the schedule for non-ASCII characters before it is uploaded. If any are found, the upload fails and says why. Off by default, because the check takes time on large schedules.
Enable conflict analysisSending and receivingChecks for conflicts, for example objects that were deleted on one side, so they can be resolved. On by default for receiving. On large schedules you may turn it off to save time. In SAP it means data is read from SAP before it is updated, which takes a little longer.
Only Include Specified MappingsReceivingOnly write the fields that are mapped in the Config. All other fields in the receiving schedule are left unchanged. For example, if you only map Description, nothing else in the host system changes.
Activity Link Rebuild Option (P6: Link Options)Receiving, Safran and P6How links between activities are recreated. Do not rebuild links: incoming links are added or updated, nothing is deleted. Rebuild only if both activities are part of the transfer: links where both activities are in the transfer are deleted and rebuilt from the sending schedule. Rebuild if at least one activity is part of the transfer: links where either activity is in the transfer are deleted and rebuilt. Delete existing destination links and rebuild: every link in the receiving schedule is deleted and rebuilt from the sending schedule.
Resource Assignment Rebuild Option (P6: Resource Assignment Rebuild Options)Receiving, Safran and P6 (not P6 XER File)How existing resource assignments on incoming activities are handled before the incoming ones are applied. Do not rebuild (default): nothing is deleted; incoming assignments are added or updated. Rebuild matching resources on incoming activities: on each incoming activity, existing assignments for the resources the sender sends are deleted, then the incoming ones are added. Assignments for other resources stay. Rebuild all resources on incoming activities: on each incoming activity, every existing assignment is deleted, then the incoming ones are added.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article