TABLE OF CONTENTS
- Schedule Core Fields
- Resource Core Fields
- Calendar Core Fields
- Profile Core Fields
- Activity Core Fields
- Resource Assignment Core Fields
- Successor Core Fields
- Structure Core Fields
CutoffDate may be re-adjusted after import based on the report schedule's points-in-time type (daily / weekly / monthly). The other fields are imported as documented below.Schedule Core Fields
| Core field name | Api field | Formula | Data type | Description |
| Description | Description | Text | The schedule's name or title. | |
| CompletedDate | CompletedDate | Date | The date the schedule finished (or is planned to finish). | |
| StartedDate | StartedDate | Date | The date the schedule started (or is planned to start). | |
| CurrentProgress | CurrentProgress | Number | The schedule's overall progress, as a percentage. | |
| CutoffDate | CutoffDate | Date | The data date / status date the schedule is current as of. | |
| Code | Code | Text | The schedule's unique identifier in the host system. |
Resource Core Fields
| Core field name | Api field | Formula | Data type | Description |
| Description | Description | Text | The resource's name or title. | |
| Code | Code | Text | The resource's unique identifier in the host system. |
Calendar Core Fields
| Core field name | Api field | Formula | Data type | Description |
| HoursPerDay | HoursPerDay | Number | The number of working hours in a standard day for this calendar. | |
| Start | Start | Date | The calendar's start date. | |
| Finish | Finish | Date | The calendar's finish date. | |
| Description | Description | Text | The calendar's name or title. | |
| Code | Code | Text | The calendar's unique identifier in the host system. |
Profile Core Fields
| Core field name | Api field | Formula | Data type | Description |
| Type | Type | Enum | The shape of the resource distribution profile. Possible values: Cumulative, Incremental. | |
| Description | Description | Text | The profile's name or title. | |
| Code | Code | Text | The profile's unique identifier in the host system. |
Activity Core Fields
| Core field name | Api field | Formula | Data type | Description |
| ActivityType | ActivityType | Enum | The kind of activity. Possible values: RegularActivity, MilestoneStart, MilestoneFinish, Hammock. | |
| Description | Description | Text | The activity's name or title. | |
| FinishAsEarlyAsPossible | FinishAsEarlyAsPossible | Boolean | Constraint: the activity should finish as early as the schedule allows. | |
| FinishNoLaterThan | FinishNoLaterThan | Date | Constraint date: the activity must finish on or before this date. | |
| MustFinishOn | MustFinishOn | Date | Constraint date: the activity must finish exactly on this date. | |
| MustStartOn | MustStartOn | Date | Constraint date: the activity must start exactly on this date. | |
| StartAsEarlyAsPossible | StartAsEarlyAsPossible | Boolean | Constraint: the activity should start as early as the schedule allows. | |
| StartAsLateAsPossible | StartAsLateAsPossible | Boolean | Constraint: the activity should start as late as the schedule allows. | |
| StartNoEarlierThan | StartNoEarlierThan | Date | Constraint date: the activity must start on or after this date. | |
| StartNoLaterThan | StartNoLaterThan | Date | Constraint date: the activity must start on or before this date. | |
| ActualFinish | ActualFinish | Date | The date the activity actually finished. | |
| ActualStart | ActualStart | Date | The date the activity actually started. | |
| ActualWorkHours | ActualWorkHours | Number | Work hours already expended on the activity. | |
| CurrentProgress | CurrentProgress | Number | The activity's progress, as a percentage. | |
| EarlyStart | EarlyStart | Date | The earliest the activity can start (forward-pass schedule date). | |
| EarlyFinish | EarlyFinish | Date | The earliest the activity can finish (forward-pass schedule date). | |
| LateFinish | LateFinish | Date | The latest the activity can finish without delaying the project (backward pass). | |
| LateStart | LateStart | Date | The latest the activity can start without delaying the project (backward pass). | |
| FreeFloatHours | FreeFloatHours | Number | Hours the activity can slip without delaying any successor. | |
| TotalFloatHours | TotalFloatHours | Number | Hours the activity can slip without delaying the project finish. | |
| PlannedWorkHours | PlannedWorkHours | Number | The planned / budgeted work hours for the activity. | |
| RemainingWorkHours | RemainingWorkHours | Number | The work hours still remaining on the activity. | |
| IsAlwaysOnSchedule | IsAlwaysOnSchedule | Boolean | Whether the activity is flagged to always be treated as on-schedule. | |
| IsCancelled | IsCancelled | Boolean | Whether the activity has been cancelled. | |
| CancelledDate | CancelledDate | Date | The date the activity was cancelled. | |
| PlannedProgress | PlannedProgress | Number | The planned progress at the data date, as a percentage. | |
| DurationHours | DurationHours | Number | The activity's duration in hours. | |
| RemainingDurationHours | RemainingDurationHours | Number | The activity's remaining duration in hours. | |
| FinishOnOrAfter | FinishOnOrAfter | Date | Constraint date: the activity must finish on or after this date. | |
| Calendar | CalendarId | Resolved on the Analytics side from the calendar reference | Reference | The calendar that governs the activity's working time. |
| Code | Code | Text | The activity's unique identifier in the host system. |
Resource Assignment Core Fields
| Core field name | Api field | Formula | Data type | Description |
| PlannedHours | PlannedHours | Number | Planned work hours assigned to the resource on the activity. | |
| ActualHours | ActualHours | Number | Actual work hours the resource has spent on the activity. | |
| CurrentProgress | CurrentProgress | Number | The progress of the resource's assignment, as a percentage. | |
| Resource | ResourceId | Resolved on the Analytics side from the Resource reference | Reference | The resource assigned to the activity. |
| Calendar | CalendarId | Resolved on the Analytics side from the Calendar reference | Reference | The calendar governing the assignment's working time. |
| Profile | ProfileId | Resolved on the Analytics side from the Profile reference | Reference | The distribution profile applied to the assignment. |
| Code | Code | Text | The assignment's unique identifier in the host system. |
Successor Core Fields
| Core field name | Api field | Formula | Data type | Description |
| Type | Type | Enum | The dependency relationship type. Possible values: StartToStart, StartToFinish, FinishToStart, FinishToFinish. | |
| LagHours | LagHours | Number | The lag, in hours, on the relationship. | |
| SuccessorObject | SuccessorObjectId | Resolved on the Analytics side from the Successor reference | Reference | The successor activity (the link target). |
| Calendar | CalendarId | Resolved on the Analytics side from the Calendar reference | Reference | The calendar used to interpret the lag. |
| Code | Code | Text | The link's unique identifier in the host system. |
Structure Core Fields
| Core field name | Api field | Formula | Data type | Description |
| Description | Description | Text | The structure's name or title. | |
| Type | Type | Enum | The kind of structure. Possible values: Wbs, FlatList, HierarchicalList. | |
| Code | Code | Text | The structure's unique identifier in the host system. |
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent